The Challenges of Building Out Tenant Space

The Challenges of Building Out Tenant Space

The design phase for this project began in late September of 2018, while the construction phase started in mid-November. Initially, the tenant was unsure of what they wanted to do for the design and layout of their new office space. To combat this, our team had to fast-track the design for the custom office space while the shell of the new Seven Oaks building was already under construction.